A common early mistake is choosing the wrong permit office. A mailing address does not always match the city boundary. The lot may be in the City of Los Angeles, another city or unincorporated Los Angeles County. Each office has its own rules and filing steps.
Confirm the permit office before applying a size, setback, parking or plan-review statement to the property.
1. Confirm the property record
Collect the facts below.
- street address and assessor parcel number;
- legal owner and parcel description;
- city limits or unincorporated Los Angeles County status;
- zoning and any applicable specific plan;
- lot area and dimensions;
- current permitted dwellings and accessory structures;
- permit history for a garage or addition;
- easements and recorded constraints; and
- survey details where boundaries or grade are uncertain.
An online map is useful for an early check. It is not a property survey or a final zoning choice.
2. Define the intended ADU path
Place the concept in one of the groups below.
- new detached construction;
- attached new construction;
- conversion of part of the main dwelling;
- conversion of an attached or detached garage or accessory structure;
- a JADU within a qualifying single-family structure;
- work on a multifamily property; or
- legalization or completion of an existing unit.
The answer controls which size, unit-count and building rules apply. If the goal is still unclear, describe who will use the unit. Add the room count, privacy needs and budget. Do not choose a project label too early.
3. Draw the site before choosing the plan
Prepare a site plan drawn to scale. Show lot lines, streets, current and planned buildings, setbacks and the space between buildings. Add easements, access, paved areas, trees, drainage and utility routes.
The LADBS standard-plan permit checklist calls for many of these items. That is why a standard plan cannot be approved from bedroom count alone.
Measure the narrowest path from the street to the work area. Note gates, overhead lines, walls and pools. Mark finished yards and places where tools or materials cannot be stored.
4. Check for conditions that need extra review
Ask the permit office or a qualified designer about each condition below.
- hillside or steep-slope conditions;
- wildfire or fire-access rules;
- coastal-zone review;
- a historic district, HPOZ or designated resource;
- flood, drainage or debris-flow details;
- protected trees or biological constraints;
- methane, liquefaction or other mapped geotechnical conditions;
- private street or limited fire access;
- rent, tenant or replacement-housing rules; or
- a pending subdivision or SB 9/SB 1123 process.
This list helps find questions. A condition shown on a map does not by itself approve or reject an ADU.
5. Test the current structure before calling it a conversion
For a garage or interior conversion, record its legal use and size. Check the slab, frame, roof, moisture, openings, ceiling height and building systems. The quote should say what stays and what must be replaced or upgraded.
The garage conversion guide gives a fuller inspection list. Do not assume that avoiding a new footprint avoids structural, energy or utility work.
6. Work utilities early
Record the current electric service, panel and meter. Add the water, sewer and gas service if gas is planned. Draw the likely routes to the ADU.
LADWP’s meter-spot page explains how it checks the panel location. It says a visit is usually set within 5–15 business days for the service shown on that page. New-build requests go to the Connection Center.
LADWP’s water installation page asks for the address, parcel number, service size and use. LADWP then issues a project Cost Letter. Main-line work and other rules can add cost and time.
Different cities, counties and utility companies use different processes. Use the utilities and site-work guide to make sure this work appears in the plan and price.
7. Use standard plans correctly
LADBS says its Standard Plan Program pre-reviews recurring designs for applicable building codes. Staff still reviews zoning and foundation conditions for the exact property. Other cities publish their own programs and limits.
A standard plan may reduce repeated design review. It may still need the work below.
- a property-specific site plan;
- foundation selection or engineering;
- grading and drainage design;
- energy documents;
- fire or historic clearances;
- utility design;
- address assignment; and
- permission from the plan owner and any related fees.
Compare standard and custom plans after the site constraints are known.
8. End with a clear choice, not a sales score
A useful report should end with one of four conclusions.
| Conclusion | Meaning | Next step |
|---|---|---|
| The idea may work | no known issue rules it out, subject to permit-office review | develop a design and utility plan for the property |
| The idea may work with changes | the type, size, location or systems should change | price only the revised plan |
| Important facts are missing | boundaries, records, structure or utilities remain unclear | obtain the missing records or inspection |
| The idea is a poor fit | limits or cost make this option unattractive | test a conversion, smaller unit or no-build option |
Avoid a percentage “buildable score” that hides which facts remain unverified.
What should an early property review cost?
There is no single Los Angeles price because the work can differ. Check what each early-review quote includes. Look for record research, field measurements, a survey and a zoning check. It should also cover unit placement, utilities, written risks, agency contact and clear next steps.
Ask whether the fee is credited toward later design, whether the company owns the work product and which conditions require specialists.
What should be ready before construction bids?
At a minimum, each bidder should get the same site facts, design and finish level. Give them the same utility assumptions, site work and exclusions too. If major questions remain, ask for an early budget with clear allowances. A fixed price is not useful until the facts support it.
The cost guide and builder comparison provide the shared fields.
Frequently asked questions
Can the City tell me exactly what an ADU will cost?
No. City and utility sources confirm rules and charges within their control. Construction price depends on the design, site, company, materials, allowances and discovered conditions.
Does state law mean every parcel can take the same ADU?
No. State law creates important approval pathways. But parcel, building-code, utility, fire, coastal, historic and other site-specific checks remain.
Do I need a survey?
Not every early screen requires a new survey. If property lines, easements, grade or the available envelope are uncertain, a survey may be necessary before relying on setbacks or final placement.
Can a website form confirm that an ADU will work?
No. A form can collect the starting facts and route the inquiry. Checking the property requires current records and review by qualified people.